Crescent Drive Water Main Replacement
Pre Construction Meeting
City of Willowick
Crescent Dr. Water Main Replacement Schedule
Starting Date of June 1st , mobilization and material delivery. (obscured signage/barricades set-up May 27th
or 28th in preparation for following week.
Excavation to begin Wednesday June 2nd, (approximately 25 days for water main installation, August 4th .)
After passing bacteriological and pressure test’s residential service connection transfers begin.
(approximately 20 days, September 1st. )
After residential service connection transfers restoration can take place, approximately 2 weeks.
Notable National Holidays during project
Memorial Day
Independence Day